德国电信(Deutsche Telekom)正在加速扩充其位于慕尼黑 Tucherpark 的 AI 工厂算力版图。该公司宣布启动 Tucherpark 2 扩建项目,追加投资近 2.5 亿欧元(约合 2.8 亿美元),以应对企业客户对高性能 AI 基础设施“强劲需求”。与此同时,公司 CEO Timotheus H?ttges 明确表示,是否参与欧盟 AI 超级工厂(Gigafactory)项目竞标仍未有定论,最终决定预计将于 12 月作出。
从“售罄”到扩建:AI 工厂的商业验证
Tucherpark 1 是德国电信与英伟达合作建设的首个 AI 工厂,于 2026 年 2 月正式上线。据德国电信企业服务部门 T-Systems CEO Ferri Abolhassan 透露,该设施仅用三个月便建成投运,比原定六个月的工期目标提前了一半,目前产能已经“售罄”。这一市场表现直接推动了二期扩建的决策。
Tucherpark 2 将在现有英伟达 Blackwell B200 系统基础上新增 B300 GPU,使这一等级的芯片数量在德国电信内部翻倍,设施总容量提升至 20 兆瓦。此外,该工厂还将继续部署英伟达 RTX Pro 6000 Blackwell Server Edition GPU。H?ttges 在新闻发布会上进一步透露,Tucherpark 3 已进入规划阶段。
值得注意的是,Abolhassan 坦言选择 Blackwell 200/300 而非下一代 Vera Rubin GPU,背后有一个颇为现实的原因——Tucherpark 设施的电梯尺寸太小,无法运输体积更大的新一代设备。这一细节也从侧面反映出老旧机房在承载前沿 AI 硬件时面临的物理瓶颈。
【关键数据】
- Tucherpark 2 追加投资: 近 2.5 亿欧元(约 2.8 亿美元)
- 设施总容量: 20 兆瓦
- AI 处理客户来电: 2026 年德国市场 260 万通
- AI 辅助开发提升 IT 生产力: 35%
- 员工日常使用 AI 工具比例: 约 83%
欧盟超级工厂:算力野心与现实阻力
欧盟 AI 超级工厂计划旨在欧洲范围内建设最多七个超大规模数据中心。招标已于 2026 年 7 月启动,中标结果预计于 2027 年初公布。H?ttges 指出,德国电信将在 12 月做出是否参与竞标的最终决定,但目前仍存在诸多待解难题。
从德国电信的评估来看,症结集中在两点:一是欧盟采购框架最终可能仅带来 10%–15% 的“有效利用率”;二是条款要求预留 60% 的容量供公共部门短期调用,这使得投资方的融资安排变得困难。H?ttges 强调,需要更多有承诺意愿的客户和切实可行的招标条款。他还表态,如果参与建设,德国电信会将其建在“最想建的地方”——巴伐利亚州。他同时坦言,德国电信自身未必需要一座超级工厂,但从德国的战略角度考虑这是必要的,前提是项目能够实现盈利。
在区域竞争层面,H?ttges 的焦虑溢于言表。他指出韩国当前的 AI 发展速度“令我们感到担忧”,仅今年一年,韩国在 AI 领域的投资就达到整个欧洲总和的五倍。欧洲在 AI 基础设施建设上必须加快节奏。
内部赋能与产业协同的双轨路径
AI 工厂只是德国电信整体 AI 战略的一个切面。在内部应用层面,2026 年 AI 在德国市场处理了 260 万通客户来电,AI 辅助软件开发使 IT 生产力提升 35%,约 83% 的员工每天都在使用 AI 工具。在网络运营侧,RAN Guardian 可以分析网络事件,并在条件变化时自动调整网络组件,实现网络智能化运维。
Abolhassan 将首个 AI 工厂定位为并非传统数据中心,而是一个完整技术栈:涵盖连接、安全、算力、基础模型、应用及咨询服务。从第一年运营中汲取的核心经验,不仅在于如何建设设施,更在于如何获取客户并让投资产生回报。他还强调了“Deutschland AG”(德国股份有限公司)式的产业协同思路,与西门子、戴姆勒等德国工业巨头的合作即是例证。
从行业视角看,德国电信的实践为传统运营商向 AI 基础设施服务商转型提供了一个可参照的样本:先以小规模设施验证商业模型,再滚动式扩建放大产能。而 12 月即将揭晓的欧盟超级工厂决策,则将成为观察欧洲能否在 AI 算力竞赛中迎头赶上的重要风向标。若招标条款能够回应投资者关切,以德国电信为代表的欧洲电信巨头或将加速入场,欧洲 AI 算力格局亦可能随之改写。
出处:DT builds out AI factory but still undecided on EU Gigafactory bid
英文原文AI & Machine Learning
Data Centers
News
DT builds out AI factory but still undecided on EU Gigafactory bid
DT expands its AI compute capacity in Munich’s Tucherpark as the initial site is now 'sold out,' but it has yet to make a decision about EU Gigafactory bid.
Anne Morris
,
Contributing Editor, Light Reading
November 9, 2026
3 Min Read
(Source: Deutsche Telekom, Norbert Ittermann)
Deutsche Telekom (DT) is expanding its so-called AI factory in Tucherpark in Munich to meet what the telco framed as "strong demand for high-performance AI infrastructure" from enterprise customers.
According to DT CEO Timotheus H?ttges, Tucherpark 1 was the first step and relates to the first DT and Nvidia AI factory that went live in February 2026. Tucherpark 2 represents the next stage at an additional cost of close to ?250 million (US$280 million) and would fill the site's capacity, H?ttges said. (See
DT and Nvidia's AI factory to launch in early 2026 in Munich
.)
The telco noted that Nvidia B300 GPUs will be added to existing Blackwell B200 systems, which it said "doubles the number of chips in this class" at DT, increasing total capacity at the facility to 20 megawatts. The AI factory will also continue to use Nvidia RTX Pro 6000 Blackwell Server Edition GPUs.
During a press conference on Monday (November 9), H?ttges said Tucherpark 3 is already in the planning stage, and also noted that "we're working on building [an AI] Gigafactory." However, he emphasized that DT has still not made a final decision on whether or not to participate in the EU's AI gigafactories project. (See
DT has 'not yet decided' on EU gigafactory bid – CEO
and
Deutsche Telekom sharpens AI gigafactory focus with Schwarz – report.
)
Under the scheme, the EU is seeking to establish up to seven
hyperscaler data centers across Europe
.
The call for tender was launched in July 2026, with the winning bids expected to be announced in early 2027.
H?ttges indicated that DT will make a decision on the matter in December, although he noted that there are still many issues to resolve. "If we build it, we'll build it where we most want to build it – in Bavaria," he said.
He said key sticking points are that the EU procurement framework might ultimately deliver only 10–15% "effective utilization," according to DT’s assessment, and that a requirement to reserve 60% of capacity
for public-sector use on short notice makes financing difficult for investors. He added that more committed customers and workable tender terms are needed.
H?ttges further commented that DT did not necessarily need a gigafactory for itself, but regarded it as a strategic necessity for Germany, provided it could earn money from it.
Indeed, he said Europe needs to up its pace on building AI infrastructure. "South Korea … is currently developing AI at a pace that gives us cause for concern. This year alone, this country is investing five times as much in AI as the whole of Europe put together," he said.
Building lessons
Ferri Abolhassan, CEO of DT's enterprise services unit T-Systems, said the first facility opened after three months, ahead of the six-month target, and is now "sold out." He described it not as a conventional data center but as a complete stack: connectivity, security, computing, foundation models, applications and consulting.
The key lesson from the first year, he said, was not just how to build a facility, but how to secure customers and make the investment pay.
The factory forms part of a broader strategy to put AI to work inside DT. The telco said AI handled 2.6 million customer calls in Germany in 2026, while AI-assisted software development improved IT productivity by 35%, and around 83% of employees use AI tools daily. It also pointed to network applications, including RAN Guardian, which analyzes network events and can automatically adjust components when conditions change.
DT's strategy also includes closer cooperation across German industry – a "Deutschland AG" approach, as Abolhassan put it, citing cooperation with Siemens and Daimler as examples.
Abolhassan did concede that DT opted to install Blackwell 200/300 GPUs as opposed to the next-generation Nvidia Vera Rubin GPUs for largely practical reasons: the elevators in the Tucherpark facility are too small to transport them.
Read more about:
Europe
About the Author
Anne Morris
Contributing Editor, Light Reading
Anne Morris is a freelance journalist, editor and translator. She has been working in the telecommunications sector since 1996, when she joined the London-based team of Communications Week International as copy editor. Over the years she held the editor position at Total Telecom Online and Total Tele-com Magazine, eventually leaving to go freelance in 2010. Now living in France, she writes for a number of titles and also provides research work for analyst companies.
See more from
Anne Morris
Want more Light Reading stories in your Google search results?
Add Us Now
Subscribe and receive the latest news from the industry.
Join 62,000+ members. Yes it's completely free.
Sign me up
Want more Light Reading stories in your Google search results?
OFC Conference and Exhibition
Experience OFC. Where the industry goes to learn, showcase technologies, forge partnerships and close deals.
Registration is Open
Popular whitepapers in 5G
More whitepapers
Sponsored Content
Antenna Monitoring for Programmable Performance
Antenna Monitoring for Programmable Performance
Jan 12, 2026
Sponsored Content
Antenna Beam Efficiency in Urban 4G/5G Networks
Antenna Beam Efficiency in Urban 4G/5G Networks
Nov 17, 2025
Our Latest Videos
More videos
Wi-Fi
Wi-Fi 8, Edge AI and the Introduction of Security and Management services
Wi-Fi 8, Edge AI and the Introduction of Security and Management services
Cable Technology
Harmonic CEO Charts a Pure-Play Broadband Future
Harmonic CEO Charts a Pure-Play Broadband Future
5G
Featured Story
Ericsson moves mmWave radio production from US to Estonia
Ericsson stops making millimeter wave radios at its 5G smart factory in Lewisville, Texas, and consolidates production at manufacturing site in Estonia.
More